Latest News, Projects and Events

MPE Manages Commissioning of Load Out System

Tuesday, March 29, 2011

Maintenance and Project Engineering (MPE) were called to assist in completing the commissioning on a train load out system at an Upper Hunter Coal Operation.

MPE Maintenance Consultant Roger Davies spent three weeks onsite overseeing the final assembly of a train load out system designed to provide train loading accuracy. Roger’s role as project manager ensured the commissioning was carried out to specification and all involved complied with the site safety and environmental management systems.

The first train was successfully loaded with all 92 wagons filled to the specified 98 tonnes.